Project: Mason Creek Greenway

Year* State Project Funding $
2004 Virginia
Mason Creek Greenway (SB-2004-VA-51)
Abstract
The project is construction of a 3-mile 10' wide bicycle/pedestrian trail, connecting the Hanging Rock Battlefield Trail (existing 2 miles) and Virginia Scenic Byway Rt. 311 to the Roanoke River Greenway (under development, 25 miles).
Region
City of Salem and Roanoke County
Byway
Route 311
Location Along Byway
The project is located in Salem, Virginia, paralleling Mason Creek from Branch Drive at Kessler Mill Road to the Roanoke River.
Project Coordinator
Liz Belcher (phone 540-776-7159)
Project Sponsor
Roanoke Valley Greenway
State Coordinator
Jeter, Erica (Virginia Department of Transportation)
Project Status
Unknown
Congressional District
Goodlatte, Bob (district 6)
$994,100.00
* denotes fiscal rather than actual year