Example 6: Proposed Budget/Cost Breakdown for an Interpretive Center (Eligibility Category: Byway Facilities):
| # Description | Total Cost | Requested | Match |
|---|---|---|---|
| 1. Master Plan | 10,000 | 8,000 | 2,000 |
| 2. Fundraising Campaign | 8,500 | 6,800 | 1,700 |
| 3. Construction | 200,000 | 160,000 | 40,000 |
| Total | $218,500 | $174,800 | $43,700 |
This example is less successful because it:
- Bundles construction costs together and costs of specific construction items are not separated out
- Includes a line item for fundraising (line item 2, $6,800). This cost is not eligible for National Scenic Byways Program (NSBP) funding because it is not consistent with the cost principles identified in the Office of Management and Budget Guidance for Grants and Agreements. See Title 2, Code of Federal Regulations http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?sid=9445200b8f94b38c09c35f3cc20d7e19&c=ecfr&tpl=/ecfrbrowse/Title02/2tab_02.tpl,Grants and Agreements (GPO electronic CFR) Part 220-Cost Principles for Educational Institutions (OMB Circular A-21) http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=9445200b8f94b38c09c35f3cc20d7e19&rgn=div5&view=text&node=2:1.1.2.3.4&idno=2, Part 225-Cost Principles for State, Local, and Indian Tribal Governments (OMB Circular A-87) http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=9445200b8f94b38c09c35f3cc20d7e19&rgn=div5&view=text&node=2:1.1.2.3.6&idno=2, Part 230-Cost Principles for Non-profit Organizations (OMB Circular A-122) http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=9445200b8f94b38c09c35f3cc20d7e19&rgn=div5&view=text&node=2:1.1.2.3.8&idno=2