| # Description |
Total Cost |
Requested |
Match |
| 1.Prepare RFPs and Select Consultant(s) for Interpretive Materials and Content Development |
5,500 |
4,400 |
1,100 |
| 2. Design Byway Logo and Highway Identity/Trailblazer Signs: Public Meeting and Review/Approval by Committee |
10,000 |
8,000 |
2,000 |
| 3. Develop Content for Brochure/Map: Consultant ($11,000), provide GIS Data and Review/Edit ($4,000), Committee Meeting, Review, Approval, and Public Meeting ($1,000) |
16,000 |
12,800 |
3,200 |
| 4. Layout and Design of Brochure/Map: Consultant ($4,000), Committee Review and Approval ($1,000), Printing ($18,750) |
24,250 |
19,400 |
4,850 |
| 5. Website: Develop Additional Content and Create: Consultant ($6,000), Domain and Hosting ($1,500), Committee Review and Approval ($1000), Review, Editing and Update ($1,000) |
9,500 |
7,600 |
1,900 |
| 6. Construct and Install Highway Identity Signs |
11,000 |
8,800 |
2,200 |
| 7. Project Administration |
10,000 |
8,000 |
2,000 |
| Total |
$86,250 |
$69,000 |
$17,250 |